Most renovation delays are decisions that were not made, not work that was not done. Here is the order things need to happen in, and what to settle before anyone starts.

Published

A villa renovation is not one project. It is a sequence of trades that each need the previous one finished, and it goes wrong in the joins. The work itself is rarely the problem. What causes the slip is a decision nobody made, an approval nobody started, or a long-lead item nobody ordered until it was needed.

This is the order to think about it in, and what to settle before anyone lifts a tool.

Before you appoint anyone

Know what you actually want to change. Not in detail, but in category. Are you replacing finishes, or moving walls? Is the kitchen staying where it is? Is the cooling system being touched? These decide which approvals you need and roughly what the job costs, and they are the questions a contractor will ask first.

Get the property surveyed properly. Not a walk-through. Measured, with levels taken and the services traced. Almost every unpleasant surprise on a renovation was visible to somebody who looked properly at the start: a floor two centimetres out over five metres, a wall that will not take a fixing, drainage that runs the wrong way for the kitchen you want.

Find the drawings if they exist. Original construction drawings, any previous renovation drawings, service routes. If they exist, they save money. If they do not, say so early so the survey can be scoped to compensate.

Establish the approval position. Which authority, which community rules, what your title or lease permits. This is the item most likely to move your completion date and the one least under a contractor’s control. Start it before anything else.

Before work starts on site

Fix the layout. Every wall in its final position, on a drawing you have signed. Layout changes after strip-out are the single most expensive category of variation, because they invalidate the services design that was drawn around them.

Settle the kitchen and the bathrooms. These carry the longest lead times and the most services coordination. A kitchen decided late holds up plumbing, electrical and the ceiling above it.

Choose the flooring. Not the exact shade, but the material and the build-up, because it sets the finished floor level and therefore every door, threshold and skirting in the property. The flooring page covers why the substrate decides most of this.

Order the long-lead items. Anything imported, anything made to measure, anything stone. These should be ordered while the site is being stripped, not when the trade that installs them is due.

Agree the payment stages. Tied to milestones you can see, not to calendar dates. And agree in writing what happens on a variation, including who can approve one, because on a live site somebody will always be asked to make a decision quickly.

The sequence on site

Roughly, and every project bends it somewhere:

  1. Strip out. Everything coming out, comes out. This is also when the property tells you the truth about itself, so leave room in the programme for what it says.
  2. Structure. Anything load-bearing, any new opening, any repair the strip-out revealed.
  3. First fix services. Electrical, plumbing, cooling, drainage. Everything that will be buried.
  4. Plaster and screed. The surfaces the finishes will sit on. This stage needs drying time and it cannot be hurried.
  5. Joinery installation. Fitted work goes in before the finished floor, not after.
  6. Flooring.
  7. Second fix and painting. Switches, sanitaryware, doors, then paint. The painting page explains why preparation is most of that job.
  8. Furniture and styling. Last, into a clean property.

The two most common expensive reorderings are laying the floor before the joinery, and painting before second fix. Both feel like progress at the time.

What to expect to go wrong

Something behind a wall will not be as expected. That is not pessimism, it is the nature of working on a building somebody else finished, possibly twice. The question is not whether it happens but whether there is contingency and a decision-making process ready when it does.

The second thing that goes wrong is decision latency. A site waits on an answer, and the answer takes four days, and that is four days on the programme that no one can recover. Agree at the start who decides, how fast, and what happens if they are travelling.

What to ask a contractor before signing

  • What did your survey find that I did not know about?
  • What is excluded from this price?
  • What are the long-lead items and when do they need ordering?
  • Which approvals are you handling and which am I?
  • Who is on site every day, and who do I call?
  • What happens to the programme if something behind a wall is wrong?

The answers are more informative than the total. A contractor who has surveyed properly will already have opinions about your property, and a contractor who has not will answer in generalities.

We take villa renovations on one contract, with the joinery made in our own workshop rather than sublet, which is the argument for a turnkey approach: when the programme slips, there is nobody else to blame it on.

Questions

Questions we get asked

Do I need approval to renovate my villa?
It depends entirely on what you are changing. Replacing finishes inside an existing layout is a different proposition from moving walls, altering the facade, changing the cooling system or adding structure, and the last group brings in the relevant authority and, for some work, the community or developer as well. Establish which category your project falls into before you fix a completion date, because approval time is not something a contractor can compress.
Can I live in the villa during the work?
Often yes, if the work is phased around you, and it usually costs more and takes longer because the site is set up and cleared repeatedly. The rooms worth protecting are the ones with water: living without a kitchen is harder than living without a sitting room. Decide this at the start, because it changes the programme rather than just the comfort.
What order should the work happen in?
Strip out, then anything structural, then services, then plaster and screed, then joinery installation, then flooring, then painting, then furniture. The most common expensive mistake is laying a finished floor before the joinery goes in, which means either damaging the floor or lifting joinery back out.
How long does a villa renovation take?
Longer than the on-site work suggests, because approvals and long-lead items sit outside the build programme. The honest answer comes after a survey. Anyone quoting a duration before seeing the property is quoting the work they hope to find rather than the work that is there.