What interior fit-out really costs in Abu Dhabi
Nobody publishes fit-out prices, so everybody guesses. Here are the ranges the market works within, what sits inside them, and the decisions that move a number more than the rate ever does.
Published
Ask what a fit-out costs and you get a shrug, or a number so wide it tells you nothing. That is frustrating when you are trying to work out whether a project is possible at all, and it pushes people into asking for a price before anyone has looked at the space. Which is how you end up comparing three quotes that describe three different jobs.
So here is the useful version. Not a price for your project, because that does not exist yet, but the ranges the Abu Dhabi market works within and, more importantly, what actually moves a number inside them.
Read the rate, then ignore it
Is a price per square metre reliable for a fit-out?
A rate per square metre is a planning tool, not a price. It tells you which conversation you are in. It does not tell you what your job costs, because two apartments of identical area can sit at opposite ends of the same band.
What the rate hides is scope. A refresh that keeps every wall and every service where it is will land near the bottom. The same room with the kitchen moved three metres, a dropped ceiling to hide the new ductwork, and fitted joinery down one wall will land near the top, and the floor area never changed.
Use the band to sanity-check a budget. Then throw it away and price the actual scope.
The six things that move the number
What affects interior fit-out cost in Abu Dhabi?
Whether the services move. This is the big one and it is the one people underestimate. Paint is cheap. Flooring is predictable. Moving a drain, adding a cooling load, or rerouting the electrical distribution pulls in coordination, authority approval and programme, and every one of those costs money. A layout change that looks small on a plan can be expensive for reasons that have nothing to do with the wall.
How much joinery there is. On most residential projects joinery is the largest single line. It is made to your dimensions, so it carries drawing time, material and skilled labour that a bought product does not. The joinery page goes into what that involves. Two identical rooms, one with a fitted wall of wardrobes and one without, are different projects.
What the joinery is made of. Painted MDF, laminated board, veneered board and solid timber are four different prices for the same drawing. So are the hinges and the runners, which is where a quote gets quietly cheapened. Ask what is specified. If it does not say, that is the answer.
The condition of what is already there. On a renovation, the substrate decides a lot. A floor that is out of level, a wall that will not take a fixing, plumbing that has to be replaced because it is going to be buried behind new finishes. None of it is visible when you take the photographs you send with your enquiry.
Stone, and anything imported. Natural stone is priced by the slab and by the wastage, and a book-matched run costs more than the same area cut from stock. Anything imported carries lead time, and lead time is a cost when the rest of the programme has to wait for it.
How fast you need it. A programme that can absorb a six-week joinery run is cheaper than one that cannot. Compression costs money in overtime, in air freight, and in the premium a supplier charges to jump a queue.
What a proper quote looks like
The document matters as much as the number. A quote you can hold someone to has:
- Line items, not a single figure. You should be able to see what the joinery costs separately from what the flooring costs.
- Materials named. Not “hardwood” but the actual specification, including the board, the finish and the hardware.
- Quantities. Square metres of tiling, linear metres of joinery, number of doors.
- What is excluded. This is the most useful section and the one most often missing.
- Payment stages tied to milestones rather than to dates.
- What happens on a variation, and who has to approve one.
If two quotes differ by thirty per cent, the difference is almost never the margin. It is the exclusions. Put them side by side and the cheap one usually turns out to be quoting a smaller job.
Where the money is worth spending
Some things you will replace in five years and some you will not. Finishes are visible and replaceable. What sits behind them is neither.
Spend on the parts that are expensive to redo: the substrate, the waterproofing, the electrical layout, the hardware inside the joinery. Save, if you need to, on the parts you can change without opening anything up. A wall colour is a weekend. A badly laid floor is the whole room again.
The other thing worth paying for is a single point of responsibility. When the design, the site work and the furniture sit with one team, nobody can tell you the problem belongs to someone else. That is the argument for a turnkey contract, and it is worth more than it looks on the quote.
Getting to a real number
Send a floor plan, or photographs and rough dimensions if you do not have one. Say what you want to change and what you want to keep. Say when you need it finished and what the budget is, because a budget shapes the design rather than limiting it, and hiding it wastes both our time.
We will tell you what the scope will cost, what we would do differently, and where we think the money is better spent. If your budget and your brief do not meet, you will hear that at the start rather than in month three.
These are the ranges the Abu Dhabi market generally works within, gathered to give you a starting point. They are not a quote from us, and no project is priced from a table. What your job costs depends on the site, the specification and the programme, and the only honest number comes after we have seen the drawings.
| Level of finish | AED per m² (2026) | What that buys |
|---|---|---|
| Refresh | 400 to 800 | Paint, flooring, light joinery, existing layout kept. No services moved, no walls touched. |
| Standard | 800 to 1,800 | Full replacement of finishes, new fitted joinery, some layout change, new lighting and switching. |
| High specification | 1,800 to 3,500 | Stone, veneered joinery, feature ceilings, altered layout, upgraded electrical and cooling. |
| Made throughout | 3,500 and up | Pieces made rather than bought, imported stone, curved and inlaid work, long lead items. |
Questions
Questions we get asked
- Why will nobody give me a price over the phone?
- Because the honest answer depends on things nobody can see down a phone line. The same 200 square metre apartment can differ by a factor of three depending on whether the walls move, what the ceiling has to hide, and whether the joinery is painted MDF or veneered. A number given before anyone has seen the drawings is either a guess or a hook, and both cost you later.
- What is the single biggest driver of the price?
- Joinery, on most residential projects. It is made to your dimensions rather than bought off a shelf, so it carries design time, material and labour in a way that paint and flooring do not. After that it is anything involving services: moving a drain or adding cooling load costs far more than moving a wall.
- Should I take the cheapest quote?
- Compare what the quotes exclude before you compare the totals. A low number usually means preparation, hardware or making good has been left out, and those reappear as variations once the work has started. Ask each contractor what happens to the price if the substrate turns out to need work.
- How much should I hold back as contingency?
- On a renovation of an existing property, plan for the fact that something behind a wall will not be as expected. On new-build shell and core, less so. Whatever figure you set, decide it before you start rather than discovering it halfway through.